Plans to resurface almost 60 roads and pavements across the authority in the next 12 months
We've drawn up proposals for a major roadworks programme which will use an additional investment of £3.5million over the next financial year to improve the condition of local residential roads.
Published: 21 March 2024
Last year, we committed a further £17.5m of capital investment for roads infrastructure over the next five years, an increase to £3.5m per year, starting in 2024-25.
The paper which will go to Councillors for approval next week includes details of the 51 roads and eight pavements which will be resurfaced in the coming year.
The projects cover all five Council ward areas across the authority, with improvements set to begin next month.
In the first five years of extra money being spent on resurfacing, a total of 172 roads and 57 pavements were improved.
The projects planned for next year will see the figures for resurfacing rise to 223 roads and 65 pavements.
As well as this additional capital funding, more than £1m of general capital funding for roads resurfacing is also available and will be spent on all classes of roads in East Renfrewshire.
Once approved, roads and pavements in the additional capital resurfacing works programme will include: Broom Crescent and Dalmeny Drive in Barrhead, Double Hedges Road and Glen Tarbert Drive in Neilston, Melford Avenue and Denholm Drive in Giffnock, Field Grove and Glenville Terrace in Busby, Lomondside Avenue and Moraine Drive in Clarkston, Borland Crescent and Kirkton Drive in Eaglesham, Floors Road in Waterfoot and Hill Avenue and Knowes Avenue in Newton Mearns.
As with previous years, the prioritisation of the resurfacing projects is based on a range of factors including: the structural condition of the road or pavement, its usage, cost of maintenance for the previous three years, number of complaints received and geographical spread.
Full list of proposed resurfacing works for 2024-25:
Road resurfacing
Completed
Bankholm Place, Busby
Beech Avenue (Beech Crescent to Eaglesham Road), Newton Mearns
Bonnyton Drive (Nos.329 to 375), Eaglesham
Borland Crescent, Eaglesham
Braidholm Road (Braidbar Farm Road to Merrycrest Avenue), Giffnock
Broom Crescent, Barrhead
Capelrig Road (at schools), Newton Mearns
Castleton Drive (Broomfield Avenue to Castlemount Avenue), Newton Mearns
Carlibar Road (A736 to Commercial Road), Barrhead
Centre Way, Barrhead
Corrie Grove, Netherlee
Cuillin Way, Barrhead
Denholm Drive, Giffnock
Dorian Drive (Seres Road to Struma Drive), Clarkston
Double Hedges Road (part), Neilston
Fereneze Road Rural (Waterworks to Gateside Road), Neilston
Field Grove, Busby
Fingleton Avenue, Barrhead
Flenders Avenue (Beechlands Drive to Hillend Crescent), Clarkston
Floors Road (part), Waterfoot
Glendoune Road, Clarkston
Glenville Terrace, Busby
Glen Tarbert Drive, Neilston
Hill Avenue, Newton Mearns
Hillview Drive (Busby Road to Mayfield Avenue), Clarkston
Kirkton Drive, Eaglesham
Knowes Avenue, Newton Mearns
Knowes Road (part), Newton Mearns
Lawrence Avenue, Giffnock
Lomondside Avenue, Clarkston
Lynton Avenue, Giffnock
Mayfield Avenue, Clarkston
Melford Avenue, Giffnock
Moraine Drive, Clarkston
Morven Drive (Seres Road to Vardar Avenue), Clarkston
North Park Avenue, Barrhead
Pollock Avenue, Eaglesham
South Park Avenue, Barrhead
The Paddock, Busby
Tormeadow Road, Newton Mearns
Woodland Crescent, Eaglesham
To be completed (2024/25)
Dalmeny Drive, Barrhead - estimated start date 3 February 2025
Humbie Road (Deil's Wood Rbt to National Speed Limit Sign), Eaglesham - estimated start date 3 March 2025
Kerr Street, Barrhead - estimated start date 3 February 2025
Malletsheugh Road Rural, Newton Mearns - estimated start date 20 January 2025
Oliphant Crescent, Clarkston - estimated start date 20 January 2025
Pollock Road, Newton Mearns - estimated start date 27 January 2025
Springfield Road (No.12 to National Speed Limit Sign), Neilston - estimated start date 17 March 2025
Strathearn Road, Clarkston - estimated start date 17 February 2025
The Quadrant, Clarkston - estimated start date 3 February 2025
William Mann Drive, Newton Mearns - estimated start date 17 March 2025
Pavement resurfacing
Completed
Glendoune Road, Clarkston
Lawrence Avenue, Giffnock
Lomondside Avenue, Clarkston
Morven Drive (Seres Road to Vardar Avenue), Clarkston
Sunnyside Drive (Golf Road to Morven Drive), Clarkston
Treemain Road, Giffnock
To be completed (2024/25)
Ormonde Avenue (Deanwood Road to Parklands Road), Netherlee - estimated start date 3 February 2025
The Quadrant, Clarkston - estimated start date 3 February 2025
Street lighting upgrades to be completed
Academy Road, Giffnock - estimated start date 30 June 2025
Ailsa Drive, Giffnock - estimated start date 21 April 2025
Airdale Avenue, Giffnock - estimated start date 30 June 2025
Arthurlie Drive, Giffnock - estimated start date 10 March 2025
Atholl Drive, Giffnock - estimated start date 17 March 2025
Balmeg Avenue, Giffnock - estimated start date 21 April 2025
Carrick Crescent, Giffnock - estimated start date 4 August 2025
Church Road (Fenwick Road to rail bridge), Giffnock - estimated start date 10 March 2025
Claremount Avenue, Giffnock - estimated start date 10 March 2025
Denholm Drive, Giffnock - estimated start date 17 March 2025
Dornoch Avenue, Giffnock - estimated start date 17 March 2025
Eastwood Avenue, Giffnock - in progress
Florence Drive, Giffnock - estimated start date 10 March 2025
Greenhill Avenue, Giffnock - estimated start date 26 May 2025
Lincuan Avenue, Giffnock - estimated start date 17 March 2025
Orchard Park, Giffnock - estimated start date 30 June 2025
Penrith Avenue, Giffnock - estimated start date 24 February 2025
Rosslea Drive, Giffnock - estimated start date 30 June 2025
St Ann's Drive, Giffnock - estimated start date 10 March 2025
St Catherine's Road, Giffnock - estimated start date 30 June 2025
Woodvale Avenue, Giffnock - in progress