Plans to resurface almost 60 roads and pavements across the authority in the next 12 months

We've drawn up proposals for a major roadworks programme which will use an additional investment of £3.5million over the next financial year to improve the condition of local residential roads.

Roads resurfacing projects

Published: 21 March 2024

Last year, we committed a further £17.5m of capital investment for roads infrastructure over the next five years, an increase to £3.5m per year, starting in 2024-25.

The paper which will go to Councillors for approval next week includes details of the 51 roads and eight pavements which will be resurfaced in the coming year.

The projects cover all five Council ward areas across the authority, with improvements set to begin next month.

In the first five years of extra money being spent on resurfacing, a total of 172 roads and 57 pavements were improved.

The projects planned for next year will see the figures for resurfacing rise to 223 roads and 65 pavements.

As well as this additional capital funding, more than £1m of general capital funding for roads resurfacing is also available and will be spent on all classes of roads in East Renfrewshire.

Once approved, roads and pavements in the additional capital resurfacing works programme will include: Broom Crescent and Dalmeny Drive in Barrhead, Double Hedges Road and Glen Tarbert Drive in Neilston, Melford Avenue and Denholm Drive in Giffnock, Field Grove and Glenville Terrace in Busby, Lomondside Avenue and Moraine Drive in Clarkston, Borland Crescent and Kirkton Drive in Eaglesham, Floors Road in Waterfoot and Hill Avenue and Knowes Avenue in Newton Mearns.

As with previous years, the prioritisation of the resurfacing projects is based on a range of factors including: the structural condition of the road or pavement, its usage, cost of maintenance for the previous three years, number of complaints received and geographical spread.

Full list of proposed resurfacing works for 2024-25:

Road resurfacing

Completed

Bankholm Place, Busby 

Beech Avenue (Beech Crescent to Eaglesham Road), Newton Mearns

Bonnyton Drive (Nos.329 to 375), Eaglesham

Borland Crescent, Eaglesham

Braidholm Road (Braidbar Farm Road to Merrycrest Avenue), Giffnock 

Broom Crescent, Barrhead 

Capelrig Road (at schools), Newton Mearns 

Castleton Drive (Broomfield Avenue to Castlemount Avenue), Newton Mearns 

Carlibar Road (A736 to Commercial Road), Barrhead 

Centre Way, Barrhead 

Corrie Grove, Netherlee 

Cuillin Way, Barrhead 

Denholm Drive, Giffnock 

Dorian Drive (Seres Road to Struma Drive), Clarkston 

Double Hedges Road (part), Neilston 

Fereneze Road Rural (Waterworks to Gateside Road), Neilston 

Field Grove, Busby 

Fingleton Avenue, Barrhead

Flenders Avenue (Beechlands Drive to Hillend Crescent), Clarkston 

Floors Road (part), Waterfoot 

Glendoune Road, Clarkston

Glenville Terrace, Busby

Glen Tarbert Drive, Neilston 

Hill Avenue, Newton Mearns

Hillview Drive (Busby Road to Mayfield Avenue), Clarkston 

Kirkton Drive, Eaglesham

Knowes Avenue, Newton Mearns

Knowes Road (part), Newton Mearns

Lawrence Avenue, Giffnock 

Lomondside Avenue, Clarkston 

Lynton Avenue, Giffnock

Mayfield Avenue, Clarkston

Melford Avenue, Giffnock 

Moraine Drive, Clarkston

Morven Drive (Seres Road to Vardar Avenue), Clarkston

North Park Avenue, Barrhead 

Pollock Avenue, Eaglesham

South Park Avenue, Barrhead 

The Paddock, Busby

Tormeadow Road, Newton Mearns 

Woodland Crescent, Eaglesham 

To be completed (2024/25)

Dalmeny Drive, Barrhead - estimated start date 3 February 2025

Humbie Road (Deil's Wood Rbt to National Speed Limit Sign), Eaglesham - estimated start date 3 March 2025

Kerr Street, Barrhead - estimated start date 3 February 2025

Malletsheugh Road Rural, Newton Mearns - estimated start date 20 January 2025

Oliphant Crescent, Clarkston - estimated start date 20 January 2025

Pollock Road, Newton Mearns - estimated start date 27 January 2025

Springfield Road (No.12 to National Speed Limit Sign), Neilston - estimated start date 17 March 2025

Strathearn Road, Clarkston - estimated start date 17 February 2025

The Quadrant, Clarkston - estimated start date 3 February 2025

William Mann Drive, Newton Mearns - estimated start date 17 March 2025

Pavement resurfacing

Completed

Glendoune Road, Clarkston

Lawrence Avenue, Giffnock

Lomondside Avenue, Clarkston 

Morven Drive (Seres Road to Vardar Avenue), Clarkston

Sunnyside Drive (Golf Road to Morven Drive), Clarkston

Treemain Road, Giffnock

To be completed (2024/25)

Ormonde Avenue (Deanwood Road to Parklands Road), Netherlee - estimated start date 3 February 2025

The Quadrant, Clarkston - estimated start date 3 February 2025

Street lighting upgrades to be completed

Academy Road, Giffnock - estimated start date 30 June 2025

Ailsa Drive, Giffnock - estimated start date 21 April 2025

Airdale Avenue, Giffnock - estimated start date 30 June 2025

Arthurlie Drive, Giffnock - estimated start date 10 March 2025

Atholl Drive, Giffnock - estimated start date 17 March 2025

Balmeg Avenue, Giffnock - estimated start date 21 April 2025

Carrick Crescent, Giffnock - estimated start date 4 August 2025

Church Road (Fenwick Road to rail bridge), Giffnock - estimated start date 10 March 2025

Claremount Avenue, Giffnock - estimated start date 10 March 2025

Denholm Drive, Giffnock - estimated start date 17 March 2025

Dornoch Avenue, Giffnock - estimated start date 17 March 2025

Eastwood Avenue, Giffnock - in progress

Florence Drive, Giffnock - estimated start date 10 March 2025

Greenhill Avenue, Giffnock - estimated start date 26 May 2025

Lincuan Avenue, Giffnock - estimated start date 17 March 2025

Orchard Park, Giffnock - estimated start date 30 June 2025

Penrith Avenue, Giffnock - estimated start date 24 February 2025

Rosslea Drive, Giffnock - estimated start date 30 June 2025

St Ann's Drive, Giffnock - estimated start date 10 March 2025

St Catherine's Road, Giffnock - estimated start date 30 June 2025

Woodvale Avenue, Giffnock - in progress

 